Production Manager Ron Fry constructed the 16 day shooting schedule for Last Sunset. This episode called for many on-set SFX and for lighting changes (day scenes are marked with a D, night scenes with a N).

Each day they would aim to film approximately 5 pages from the script. Note that certain scenes were "to be scheduled later".

GROUP THREE PRODUCTIONS LIMITED

"SPACE 1999" TELEVISION SERIES

SHOOTING SCHEDULE No. 1
"THE LAST SUNSET"
EPISODE 11
DIRECTOR: CHARLES CRICHTON

Issued: 22nd. July 1974

GROUP PRODUCTIONS LIMITED

"SPACE 1999" TELEVISION SERIES. PAGE 1

SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)

DATE STAGE SET SCENE NOS. PAGES CHARACTERS ESSENTIAL REQUIREMENTS
TUESDAY
23RD JULY
1974
M INT. COMMAND MODULE

TV Link:- (Mission
Section)

5.7.10.12.14.17.19.
21.27.28.29.34.90.
117pt.95.99.103.105.
110.121.134.140.143.
163.164pt.170.178.
5 1/8 KOENIG
MORROW
CARTER
DR.MATHIAS
JOHNSON
Live TV link to sets.
Buffeting fx on
eagle.
M INT. PASSENGER MODULE 35.85A.88A.91.96.
101.108.
1 HELENA
MORROW
CARTER
SANDRA
JOHNSON
Buffeting ' on
eagle
WEDNESDAY
24TH JULY
1974
L INT. MAIN MISSION/KOENIG'S
OFFICE
TV Link:- (Technical
section)
3.6.8.20.23.30.32.36.
45.47pt.128(N).93B.139.
117pt.141.56pt(D).
5 1/8 KOENIG
HELENA
BERGMAN
MORROW
CARTER
SANDRA
KANO
DR.MATHIAS
TANYA
M/M OPERATIVES
Live TV link to sets.
L/Cameraman:
Note: change lighting
Night to Day.
THURSDAY
25TH JULY
1974
L INT. MAIN MISSION/KOENIG'S
OFFICE
TV Link:- (Medical Centre)
Comp.56.86.58.62.97.
106.116.181pt.(D)
5 1/4 KOENIG
HELENA
BERGMAN
MORROW
CARTER
SANDRA
KANO
DR.MATHIAS
TANYA
M/M OPERATIVES
Live TV link to sets.
Matte screen req.
GROUP PRODUCTIONS LIMITED

"SPACE 1999" TELEVISION SERIES. PAGE 2

SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)

DATE STAGE SET SCENE NOS. PAGES CHARACTERS ESSENTIAL REQUIREMENTS
FRIDAY
26TH JULY
1974
L INT. MAIN MISSION/KOENIG'S
OFFICE
TV Link:- (Technical section)
Comp 181.183pt(D).
47pt(N).49.50.51.
53.93.79.82.81.84.
93c(D).
5 1/8 KOENIG
HELENA
BERGMAN
MORROW
CARTER
SANDRA
KANO
DR.MATHIAS
TANYA
M/M OPERATIVES
Live TV link to sets.
Matte screen req..
SFX: Rain on window
fx.
L/Cameraman:
Lighting changes on
Scs.*83pt.47pt.49.
SATURDAY
27TH JULY
1974

SUNDAY
28TH JULY
1974

NO

SHOOTING
GROUP PRODUCTIONS LIMITED

"SPACE 1999" TELEVISION SERIES. PAGE 3

SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)

DATE STAGE SET SCENE NOS. PAGES CHARACTERS ESSENTIAL REQUIREMENTS
MONDAY
29TH JULY
1974
L INT. MAIN MISSION/KOENIG'S
OFFICE

71.76.137.156(DAY) 3 1/8 KOENIG
BERGMAN
KANO
M INT.CRASHED PASSENGER
MODULE
119pt(D) 1 HELENA
MORROW
CARTER
SANDRA
TUESDAY
30TH JULY
1974
M INT.CRASHED PASSENGER
MODULE
Comp 119.123.129.
132(D).136.146pt(N)
4 1/2 HELENA
MORROW
CARTER
SANDRA
L/Cameraman: Note light
change day to night.
SFX: Lunar dust to
pour in module fx.
WEDNESDAY
31ST JULY
1974
M INT.CRASHED PASSENGER
MODULE
Comp 146.148.150(N).
165(D)
1 1/2 HELENA
MORROW
CARTER
SANDRA
L/Cameraman: Note light
changes Night to Day

M EXT. MOON SURFACE-
EXT & INT MORROW' SHACK
154(D) 3 3/8 HELENA
MORROW
CARTER
SANDRA
SFX: Wind machine for
lunar breeze.
THURSDAY
1ST AUGUST
1974
M EXT. MOON SURFACE-
EXT & INT MORROW'S SHACK
158.159.161.173.174.
176.179.180pt(D)
4 5/8 HELENA
MORROW
CARTER
SANDRA
SFX: Wind machines for
lunar wind and blast fx.
Camera Dept: Extra
camera required.

GROUP PRODUCTIONS LIMITED

"SPACE 1999" TELEVISION SERIES. PAGE 4

SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)

DATE STAGE SET SCENE NOS. PAGES CHARACTERS ESSENTIAL REQUIREMENTS
FRIDAY
2ND AUGUST
1974
M EXT. MOON SURFACE-
MORROW'S SHACK & CRASH
SITE
Comp 180.124.125.126pt.
130.153.167.169(D).
147.149.151(N)
2 3/8 KOENIG
HELENA
MORROW
CARTER
SANDRA

Stunt Doubles:
Koenig
Morrow
L/Cameraman: Note
light change from Day
to Night
Camera Dept: Extra
camera required
SFX: Dust storm
and wind machine
required.
L INT. TECHNICAL SECTION
& CORRIDOR
38pt(N) 1 1/2 KOENIG
HELENA
BERGMAN
CARTER
TECHNICIAN
SFX: White vapour
fx in Technical
section.
SATURDAY
3RD AUGUST
1974

SUNDAY
4TH AUGUST
1974

NO

SHOOTING
GROUP PRODUCTIONS LIMITED

"SPACE 1999" TELEVISION SERIES. PAGE 5

SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)

DATE STAGE SET SCENE NOS. PAGES CHARACTERS ESSENTIAL REQUIREMENTS
MONDAY
5TH AUGUST
1974
L INT. TECHNICAL SECTION
& CORRIDOR
Comp 38.39.40.41(N).
65.67.69.72.85.145
(D),
4 5/8 KOENIG
HELENA
BERGMAN
CARTER
TECHNICIANS
(MORROW)
(KANO)
Live TV link to sets.

SFX: White vapour &
gas fx. Gale of white
vapour and door to
burst open.
Wind machine for
breeze fx.
L/Cameraman: Note
light change from
Night to Day
TUESDAY
6TH AUGUST
1974
M EXT.MOON SURFACE -
Airlock - Badmington -
Rocky area.
57.59.61.63.Burn-
in for Sc.62.64.66.
68.89.155.70.73A.
74pt.78(D).
4 1/8 MORROW
CARTER
SANDRA
TANYA
OTHER ALPHANS
Art Dept: Window
section for Sc.68.
Rostrum for Sc.155.
SFX: Wind machine for
lunar breeze.
L/Cameraman: Lighting
fx as from 73A.
Editor notes:

1) EXT. MOON SURFACE - Scs.80.83(D) to be scheduled later.
2) Standard series opening for Sc.No.25.

SPECIAL EFFECTS SET & SCENE LIST:

EXT. SPACE SKY: 1.4.9.11.13.15.16.18.22.24.26.52.75.77.182.
EXT.LUNAR SKY: 94.98.100.102.104.107.109.111.112.126pt.127.172.183pt.
EXT.MOON BASE ALPHA: 2.31.33.37.44.46.54.55.73.74pt.88.92.93A.117.138.142.144.157.183pt.Plus burn-in for Scs.28.181.
EXT.LUNAR SURFACE: 48.60.112.115.118.120.131.133.135.152.160.162.164pt.166.168.171.177
INT.MAINTENANCE: 42
INT.ALPHA: 43
INT.TRAVEL TUBE: 87

Ron Fry,