Production Manager Ron Fry constructed the 16 day shooting schedule for Last Sunset. This episode called for many on-set SFX and for lighting changes (day scenes are marked with a D, night scenes with a N).
Each day they would aim to film approximately 5 pages from the script. Note that certain scenes were "to be scheduled later".
GROUP THREE PRODUCTIONS LIMITED |
"SPACE 1999" TELEVISION SERIES |
|
SHOOTING SCHEDULE No. 1 "THE LAST SUNSET" EPISODE 11 DIRECTOR: CHARLES CRICHTON |
||
Issued: 22nd. July 1974 |
GROUP PRODUCTIONS LIMITED |
"SPACE 1999" TELEVISION SERIES. PAGE 1 |
SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)
DATE | STAGE | SET | SCENE NOS. | PAGES | CHARACTERS | ESSENTIAL REQUIREMENTS |
TUESDAY 23RD JULY 1974 |
M | INT. COMMAND MODULE TV Link:- (Mission |
5.7.10.12.14.17.19. 21.27.28.29.34.90. 117pt.95.99.103.105. 110.121.134.140.143. 163.164pt.170.178. |
5 1/8 | KOENIG MORROW CARTER DR.MATHIAS JOHNSON |
Live TV link to sets. Buffeting fx on eagle. |
M | INT. PASSENGER MODULE | 35.85A.88A.91.96. 101.108. |
1 | HELENA MORROW CARTER SANDRA JOHNSON |
Buffeting ' on eagle |
|
WEDNESDAY 24TH JULY 1974 |
L | INT. MAIN MISSION/KOENIG'S OFFICE TV Link:- (Technical section) |
3.6.8.20.23.30.32.36. 45.47pt.128(N).93B.139. 117pt.141.56pt(D). |
5 1/8 | KOENIG HELENA BERGMAN MORROW CARTER SANDRA KANO DR.MATHIAS TANYA M/M OPERATIVES |
Live TV link to sets. L/Cameraman: Note: change lighting Night to Day. |
THURSDAY 25TH JULY 1974 |
L | INT. MAIN MISSION/KOENIG'S OFFICE TV Link:- (Medical Centre) |
Comp.56.86.58.62.97. 106.116.181pt.(D) |
5 1/4 | KOENIG HELENA BERGMAN MORROW CARTER SANDRA KANO DR.MATHIAS TANYA M/M OPERATIVES |
Live TV link to sets. Matte screen req. |
GROUP PRODUCTIONS LIMITED |
"SPACE 1999" TELEVISION SERIES. PAGE 2 |
SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)
DATE | STAGE | SET | SCENE NOS. | PAGES | CHARACTERS | ESSENTIAL REQUIREMENTS |
FRIDAY 26TH JULY 1974 |
L | INT. MAIN MISSION/KOENIG'S OFFICE TV Link:- (Technical section) |
Comp 181.183pt(D). 47pt(N).49.50.51. 53.93.79.82.81.84. 93c(D). |
5 1/8 | KOENIG HELENA BERGMAN MORROW CARTER SANDRA KANO DR.MATHIAS TANYA M/M OPERATIVES |
Live TV link to sets. Matte screen req.. SFX: Rain on window fx. L/Cameraman: Lighting changes on Scs.*83pt.47pt.49. |
SATURDAY 27TH JULY 1974 SUNDAY |
NO |
SHOOTING |
GROUP PRODUCTIONS LIMITED |
"SPACE 1999" TELEVISION SERIES. PAGE 3 |
SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)
DATE | STAGE | SET | SCENE NOS. | PAGES | CHARACTERS | ESSENTIAL REQUIREMENTS |
MONDAY 29TH JULY 1974 |
L | INT. MAIN MISSION/KOENIG'S OFFICE |
71.76.137.156(DAY) | 3 1/8 | KOENIG BERGMAN KANO |
|
M | INT.CRASHED PASSENGER MODULE |
119pt(D) | 1 | HELENA MORROW CARTER SANDRA |
||
TUESDAY 30TH JULY 1974 |
M | INT.CRASHED PASSENGER MODULE |
Comp 119.123.129. 132(D).136.146pt(N) |
4 1/2 | HELENA MORROW CARTER SANDRA |
L/Cameraman: Note light change day to night. SFX: Lunar dust to pour in module fx. |
WEDNESDAY 31ST JULY 1974 |
M | INT.CRASHED PASSENGER MODULE |
Comp 146.148.150(N). 165(D) |
1 1/2 | HELENA MORROW CARTER SANDRA |
L/Cameraman: Note light changes Night to Day |
M | EXT. MOON SURFACE- EXT & INT MORROW' SHACK |
154(D) | 3 3/8 | HELENA MORROW CARTER SANDRA |
SFX: Wind machine for lunar breeze. |
|
THURSDAY 1ST AUGUST 1974 |
M | EXT. MOON SURFACE- EXT & INT MORROW'S SHACK |
158.159.161.173.174. 176.179.180pt(D) |
4 5/8 | HELENA MORROW CARTER SANDRA |
SFX: Wind machines for lunar wind and blast fx. Camera Dept: Extra camera required. |
GROUP PRODUCTIONS LIMITED |
"SPACE 1999" TELEVISION SERIES. PAGE 4 |
SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)
DATE | STAGE | SET | SCENE NOS. | PAGES | CHARACTERS | ESSENTIAL REQUIREMENTS |
FRIDAY 2ND AUGUST 1974 |
M | EXT. MOON SURFACE- MORROW'S SHACK & CRASH SITE |
Comp 180.124.125.126pt. 130.153.167.169(D). 147.149.151(N) |
2 3/8 | KOENIG HELENA MORROW CARTER SANDRA Stunt Doubles: Koenig Morrow |
L/Cameraman: Note light change from Day to Night Camera Dept: Extra camera required SFX: Dust storm and wind machine required. |
L | INT. TECHNICAL SECTION & CORRIDOR |
38pt(N) | 1 1/2 | KOENIG HELENA BERGMAN CARTER TECHNICIAN |
SFX: White vapour fx in Technical section. |
|
SATURDAY 3RD AUGUST 1974 SUNDAY |
NO |
SHOOTING |
GROUP PRODUCTIONS LIMITED |
"SPACE 1999" TELEVISION SERIES. PAGE 5 |
SHOOTING SCHEDULE No. 1 - "THE LAST SUNSET" (EPISODE 11)
DATE | STAGE | SET | SCENE NOS. | PAGES | CHARACTERS | ESSENTIAL REQUIREMENTS |
MONDAY 5TH AUGUST 1974 |
L | INT. TECHNICAL SECTION & CORRIDOR |
Comp 38.39.40.41(N). 65.67.69.72.85.145 (D), |
4 5/8 | KOENIG HELENA BERGMAN CARTER TECHNICIANS (MORROW) (KANO) |
Live TV link to sets. SFX: White vapour & gas fx. Gale of white vapour and door to burst open. Wind machine for breeze fx. L/Cameraman: Note light change from Night to Day |
TUESDAY 6TH AUGUST 1974 |
M | EXT.MOON SURFACE - Airlock - Badmington - Rocky area. |
57.59.61.63.Burn- in for Sc.62.64.66. 68.89.155.70.73A. 74pt.78(D). |
4 1/8 | MORROW CARTER SANDRA TANYA OTHER ALPHANS |
Art Dept: Window section for Sc.68. Rostrum for Sc.155. SFX: Wind machine for lunar breeze. L/Cameraman: Lighting fx as from 73A. |
1) EXT. MOON SURFACE - Scs.80.83(D) to be scheduled later. |
SPECIAL EFFECTS SET & SCENE LIST:
EXT. SPACE SKY: 1.4.9.11.13.15.16.18.22.24.26.52.75.77.182. | |
EXT.LUNAR SKY: 94.98.100.102.104.107.109.111.112.126pt.127.172.183pt. | |
EXT.MOON BASE ALPHA: 2.31.33.37.44.46.54.55.73.74pt.88.92.93A.117.138.142.144.157.183pt.Plus burn-in for Scs.28.181. | |
EXT.LUNAR SURFACE: 48.60.112.115.118.120.131.133.135.152.160.162.164pt.166.168.171.177 | |
INT.MAINTENANCE: 42 | |
INT.ALPHA: 43 | |
INT.TRAVEL TUBE: 87 |
Ron Fry,
PRODUCTION MANAGER